A 78-second film: a fast construction montage, then mechanical completion and turnover, pre-commissioning and loop checks, commissioning system by system, and first LNG. Each stage names the service lines that carry it. The plant is illustrative, sized from public engineering sources. It is not any real facility.
The point is the model behind it: one digital twin of the plant that tracks completions and turnover, trains crews and owners' operators, and turns into film and interactive pages for your own proposals. This page is one of those.
The plant model behind the film, live in your browser. Scrub the build from site preparation to first LNG, tap any piece of equipment to see what it does and which service lines touch it, or switch on X-ray to follow the gas from inlet to tank. Completions mode shows the plant system by system from mechanical completion to ready for start-up; Train runs a site orientation and a scored procedure drill.
Systems and subsystems on the 3D plant, coloured by status from mechanical completion to ready for start-up. Punch items (Cat A/B) pinned to the equipment they belong to, loop-check and SIS function-test status per system, turnover-package progress. It reads from the completions system you already run, by import and export; it does not replace it.
Commissioning & completions · SIS & automation · QA/QC inspection · Owner representation
Site orientation, procedure drills (an ESD valve stroke test, LOTO, a start-up step) and rule-scored assessments on the real layout, on laptop, phone or VR. Records export to your LMS (xAPI, cmi5). The same modules package the O&M training and qualification you deliver to owners.
Commissioning & completions · Specialty maintenance
A build and commissioning film plus an interactive plant page like this one, made for an owner pursuit from public filings or the drawings you share, with your service lines mapped stage by stage. It shows owners how you would carry their project from mechanical completion to first product.
All service lines
Commissioning sequence and crew-loading what-ifs by system; turnaround scenarios for crew density, cranes, laydown and shifts; an equipment register with maintenance plans linked to the owner's CMMS.
Planning & scheduling · Project coordination · Specialty maintenance · Rotating equipment
A train of this class (about 5 million tonnes a year) makes roughly 13,700 tonnes of LNG a day. Every day between mechanical completion and first LNG is product the owner is not shipping, and completions and commissioning sit on that critical path.
Illustrative arithmetic, not a forecast: 5 million tonnes a year / 365 days.
Status questions answered from one view instead of a spreadsheet chase; punch and rework visible against the equipment and the system they block; turnover gaps seen while there is still time to close them; crews arriving already oriented to the site.
One system on one live project (with the owner's agreement), or this representative LNG unit. Completions status and punch items on the twin, fed from your completions export. One onboarding module and one procedure drill for a crew mobilising to that site.
A completions export for that system (subsystems, ITRs, loop checks, punch); the P&IDs and general arrangement for its area; one procedure to turn into a drill; a contact on the project team.
Success measures agreed up front: time to answer a status question, rework caught before turnover, onboarding time for a new crew member. Then a decision on scale-up.
Also on the same model: plot plan and code checks (PDF), and OpenUSD and MuJoCo export for robot simulation.
Orientation to the real layout · step-by-step SOPs on the actual equipment · repeatable emergency drills (gas alarm, ESD, spill, fire, power loss) · fixed-rule scoring with a full audit trail.
Required hands-on evaluations and live drills, such as the workplace evaluation in OSHA 29 CFR 1910.178(l) or the hands-on fire drills in 49 CFR 193.2717. Training prepares crews for them, and certificates say so.